Update from DCAM regarding the demolition and site preparation of the Courthouse site

from James Errickson, DPD

Wednesday, October 14, 2009

To the neighborhood of the future Lowell Courthouse;

At this time, Testa has completed the demolition of the four structures which were part of this project. The site has been graded, construction fence removed, and equipment is being demobilized. Revere Street has been paved and reopened to traffic.

Within the next few days, all construction equipment, the office trailer, etc, will be removed from the site.

We want to thank you for your patience during the construction project and look forward to the redevelopment of the entire Hamilton Canal District.